Capacity Planning, High Availability and Disaster Recovery

Design for failure with redundancy, load testing, capacity forecasts and recovery plans measured in RPO and RTO.

Advanced · about 5 hours · difficulty 4/5

Learn first: SLIs, SLOs and Error Budgets, Cloud Networking and Storage Design

Reliability is designed in, not added after an outage. This topic covers the planning side of SRE.

High availability patterns

  • Remove single points of failure: at least two of everything across zones, with health-checked load balancing.
  • Graceful degradation: serve cached or partial results when a dependency fails.
  • Timeouts, retries with backoff and jitter, circuit breakers so one slow dependency does not cascade.
  • Bulkheads and rate limits to isolate noisy tenants.

Capacity planning

  • Know your headroom: how much traffic you can take before latency or errors climb.
  • Load test with tools like k6, Locust or JMeter against realistic traffic shapes, and find the first bottleneck.
  • Forecast from growth trends and planned launches; account for zone failure (N+1 capacity).
  • Autoscaling helps but has limits: warm-up time, quotas, database connections.

Disaster recovery

  • RPO (recovery point objective): how much data you can afford to lose.
  • RTO (recovery time objective): how long you can be down.
  • Strategies from cheapest to fastest: backup and restore, pilot light, warm standby, multi-site active-active.
  • Keep backups in another region and account, and codify the rebuild in IaC.
  • Test the plan: game days and restore drills. An untested DR plan is a hope, not a plan.

Good enough to move on: you can load test a service to find its limit, name its single points of failure, and write a DR plan with RPO, RTO and a strategy that matches them.

Key concepts

  • Removing single points of failure
  • Timeouts, retries and circuit breakers
  • Graceful degradation
  • Load testing with k6 or Locust
  • Capacity forecasting and headroom
  • RPO and RTO
  • DR strategies: backup to active-active
  • Game days and restore drills

Mini project

Load test your demo service with k6 to find its breaking point, document the bottleneck and fix it, then write a DR plan with RPO and RTO and rehearse restoring it in a second region from backups.

Check yourself

A business says it can lose at most 5 minutes of data and be down at most 1 hour. Which DR strategy fits, and what does it cost compared with backup and restore?